Ch 6 — Planning, Scheduling & Monitoring
Ch 6 — Planning, Scheduling & Monitoring
Construction Engineer Master Reference | RahulNew 2026
─────────────────────────────────────────────────────────────────────────────────────
Why Planning Matters on Site
Planning is the process of deciding in advance what work will be done, when, by whom, and with what resources. Without a plan, every site operates reactively — problems appear before solutions. With a plan, problems are anticipated and resources are ready.
Plan → Schedule → Execute → Monitor → Control → Update
The three most used planning tools on Indian construction sites:
Bar Chart (Gantt Chart) — for activity scheduling and progress tracking
CPM Network — for identifying critical activities and float
S-Curve — for monitoring cumulative progress vs planned
Work Breakdown Structure (WBS)
A WBS breaks the entire project into manageable work packages. It is the foundation of all scheduling.
Level
Description
Example
Level 1
Project
G+2 Residential Building
Level 2
Phase
Sub-structure / Super-structure / Finishing
Level 3
Stage
Foundation / Plinth / Ground Floor / First Floor
Level 4
Activity
Footing excavation / PCC / RCC footing / Plinth beam
Level 5
Task
Setting out / Shuttering / Steel / Concreting / Curing
Bar Chart (Gantt Chart) — Complete Guide
3.1 What Is a Bar Chart?
A bar chart is a time-scaled diagram where each activity is shown as a horizontal bar. The length of the bar represents the activity duration. It is the most widely used planning tool at the site level.
3.2 Typical Activity List — G+2 Residential Building
S.No
Activity
Duration (Weeks)
Predecessor
Resources Required
1
Site mobilisation & setting out
1
—
Site Engr, Surveyor
2
Excavation — all footings
2
1
JCB, Labourers
3
PCC below footings
1
2
Mason, Mixer, Helpers
4
RCC isolated footings
2
3
Mason, Steel fixer, Carpenter, Vibrator
5
RCC plinth beam
1
4
Mason, Steel fixer, Carpenter
6
DPC + plinth filling + compaction
1
5
Mason, Compactor, Helpers
7
RCC GF columns (up to slab soffit)
2
6
Mason, Steel fixer, Carpenter
8
RCC GF beam + slab (formwork+steel+concrete)
2
7
All trades + pump
9
Brickwork — GF walls
2
8 (after 7-day cure)
Mason, Helpers
10
RCC FF columns
2
8
Mason, Steel fixer, Carpenter
11
RCC FF beam + slab
2
10
All trades
12
Brickwork — FF walls
2
11 (after 7-day cure)
Mason, Helpers
13
Internal plaster — GF + FF
3
9,12
Plaster mason, Helpers
14
External plaster
2
12
Plaster mason, Scaffolding
15
Flooring — all floors
2
13
Tile mason, Helpers
16
MEP rough-in (plumbing, electrical)
3
9 start
Plumber, Electrician
17
MEP finishing (fixtures, switches)
1
16
Plumber, Electrician
18
Painting — all areas
2
13,14
Painter, Helpers
19
Doors, windows, hardware
1
13
Carpenter
20
External works, cleaning, handover
1
18,19
All trades
Loading...
MARKER LEGEND
DATA TABLE — Values from your sheet / common reference
1. ROLE OF PLANNING IN PROJECTS
Planning = deciding what to do, when, how long it will take, and what resources are needed to finish the project in time and within budget.
Main outputs of planning:
Project bar chart / Gantt chart.
Critical Path Method (CPM) network.
Resource plan (labour, machinery, materials).
S‑curve (planned vs actual progress).
2. BAR CHART / GANTT CHART
Bar chart (Gantt chart) shows activities on time scale, with start and finish weeks/days.