Ch 8 — QA/QC & Testing
Ch 8 — QA/QC & Testing
Ch 8 — QA/QC & Testing
Construction Engineer Master Reference | RahulNew 2026
─────────────────────────────────────────────────────────────────────────────────────
Aspect
Quality Assurance (QA)
Quality Control (QC)
Focus
Process
Product / Output
Approach
Preventive — stop defects before they happen
Detective — find defects after work is done
When
Before and during work
During and after work
Tools
ITP, Method Statement, Approvals, Audits
Inspection, Testing, Checklists, Measurement
Responsibility
Project Manager, QA Manager
Site Engineer, QC Inspector
Example
Preparing pre-pour checklist before concrete
Measuring cover and checking cube test result
IS Code Reference
IS 14001 (EMS), IS 18001 (OHS), ISO 9001
IS 456, IS 516, IS 1199, IS 2386
Output
System compliance record
Pass / Fail test result
Inspection & Test Plan (ITP)
An ITP is a document that defines what will be inspected, when, by whom, and what the acceptance criteria are for every major activity.
Activity
Inspection Point
Who Inspects
Test / Check
Acceptance Criteria
Record
Excavation
Before PCC
Site Engr + Client
Level, dimensions, soil condition
As per drawing ± 25mm
MB entry
PCC
During pour
Site Engr
Thickness, level, mix
100mm min, M10
MB + level record
Footing steel
Before pour
Site Engr + Struct Engr
Dia, spacing, cover, BBS match
As per drawing + IS 456
Pre-pour checklist
Footing concrete
During pour
Site Engr
Slump test, cube samples
Slump 25–75mm, fck 20
Cube register, slump record
Column steel
Before pour
Site Engr
Dia, stirrups, cover, starter bars
As per BBS + 40mm cover
Pre-pour checklist
Column concrete
During pour
Site Engr
Slump, cube, plumb after pour
Slump 25–75mm, plumb ≤ L/500
Cube register
Slab steel
Before pour
Site Engr + Struct Engr
Main steel, distribution, chairs
As per drawing + IS 456
Pre-pour checklist
Slab concrete
During pour
Site Engr
Slump, cube, level
Slump 75–100mm, level ± 5mm
Cube register
Brickwork
During laying
Site Engr
Plumb, level, joint thickness
Plumb L/500, joint 10mm
Daily inspection register
Plaster
After application
Site Engr
Thickness, hollowness, cracks
12mm int, 20mm ext, no hollow
Inspection register
Waterproofing
After application
Site Engr + Waterproof vendor
Flood test 48 hrs
No leakage in 48 hours
Flood test record
Tiling
After laying
Site Engr
Hollow check, level, joint
No hollow, ±3mm level, 2mm joint
Inspection register
Concrete Cube Test — IS 516:1959
3.1 Cube Test Procedure — Step by Step
Sample concrete at the point of placement — not at the mixer (IS 1199)
Fill mould in 3 layers — each layer tamped 35 times with tamping rod
Loading...
MARKER LEGEND
DATA TABLE — Values from your sheet / common reference
1. ROLE OF QA/QC IN PROJECTS
QA (Quality Assurance) = systems & procedures to ensure quality is built in.
QC (Quality Control) = tests & inspections to verify actual quality achieved.
Main objectives:
Ensure materials, workmanship and tests follow IS codes and specifications.
Detect and rectify defects early.
Provide documentary proof (registers, test reports) for clients and authorities.
2. CONCRETE CUBE TESTING
Concrete cube test measures compressive strength of concrete at 7 & 28 days.